69th Avenue and Anoka Street Rehabilitation Project

Project Updates

Below is a list of project updates, with the most recent update at the top. If you have any questions, please call our Engineering Division at 763-572-3554.

August 7, 2020

Coming up the week of August 10 there will be final preparation for paving and paving will begin. Reminders about parking and what to expect when the asphalt is placed is found in the emailed update below. 

Official Emailed Public Notice August 7 (PDF)

July 24th, 2020

The week of July 27th the contractor will be starting traffic light revisions, continuing concrete work and preparing for paving. More information can be found in the latest emailed notice found below. 

Official Mailed Public Notice July 24th (PDF)

June 26th, 2020

The week of June 29th concrete work will continue taking place along the south side of 69th Avenue. Please note that dates are subject to change due to weather. More information is included in the weekly construction update emailed to residents on Friday, June 26th and linked below.

Official Mailed Public Notice June 26th (PDF)

June 25, 2020

Concrete Work 

Concrete work is going to taking place along 69th Avenue from Central Avenue to County Rd H on Friday, June 26th. If curb has been removed from the front of your driveway, please park vehicles on adjacent streets (Siverts Lane or Shamrock Lane) prior to 7:00 am on Friday, June 26th. A notice was hand delivered to all affected residents and can be viewed below.

Official mailed public notice June 25th (PDF)

June 19, 2020

Parking reminder - please do not park cars on 69th Avenue or Anoka Street from 7:00 am to 7:00 pm Monday through Friday to ensure the contractor has the space needed to complete the project. Construction will continue the week of June 22nd with grading the roadway and storm sewer work. More information is in this week’s public notice.

Official mailed public notice June 19th (PDF)

June 12, 2020

Construction will continue the week of June 15th with removal of concrete curb and gutter. The emailed public notice for this week also includes some important information about parking and temporary mailboxes. Please contact the Engineering Division with questions or concerns. 

Official Mailed Public Notice June 12 (PDF)



Subscribe to Email or Text Notifications

To subscribe to email or text notifications, visit our Fridley 4U notifications page and enter your email. Select whether you would like to receive your notifications by text, email or both. 

Below will be list of various topics you can subscribe to, including 69th Avenue and Anoka Street Rehabilitation Project.

Note: Please remember to set your spam blocker to allow mail from listserv@civicplus.com.  

Map of Area to be Resurfaced

Street Resurfacing_2018_mailing


Construction Information and Frequently Asked Questions 

This handout answers questions and gives general information about what to expect during construction. Find more information online or call us at 763-572-3554 with further questions.

View the construction layout 

Resident Questionnaire

It is helpful for us to gather information about your property ahead of time, such as any plans to repair or replace water or sewer service, driveway widening and replacement and if you have an irrigation system or pet fence. It is also helpful if we can find out if you have any accessibility issues or if you have a home business or special event planned. We want to work with you to ensure you have proper access to your property. Please fill out this questionnaire with this information. If you have difficulty downloading the document or need assistance filling it out, please contact Engineering at 763-572-3554.